HOW TO AVOID COSTLY MISTAKES DURING ELEVATOR MODERNIZATION
A Technical Guide for Building Owners, Property Managers, and Facility Directors
Prepared by Senawi Group Consulting LLC
Independent Elevator, Escalator, and Moving Walk Consulting
Introduction
Elevator modernization represents one of the more significant capital investments a building owner may undertake. Depending on the equipment type, number of elevators, building conditions, and project scope, modernization costs can range from hundreds of thousands to several million dollars.
Although modernization can improve equipment reliability, passenger safety, energy efficiency, operating performance, and long-term maintainability, poorly planned projects can result in substantial cost overruns, unnecessary equipment replacement, extended shutdowns, and unexpected maintenance expenses.
One of the most common mistakes building owners make is approaching elevator modernization primarily as an equipment replacement project rather than a comprehensive engineering, planning, and construction undertaking.
A successful modernization begins long before the first elevator is taken out of service.
Understanding the technical and financial considerations before approving a modernization proposal can help owners avoid expensive mistakes and protect their investment for decades.
1. Modernizing Equipment Without a Comprehensive Condition Assessment
One of the first mistakes is assuming that all existing elevator components must be replaced simply because the equipment is aging.
Elevator systems contain multiple interconnected components, each with different service lives, operating conditions, and replacement requirements.
A comprehensive assessment should evaluate:
• Elevator controllers, drives, and electrical systems.
• Traction machines, motors, brakes, and bearings.
• Hydraulic power units, valves, cylinders, and piping.
• Door operators, hoistway door equipment, and interlocks.
• Suspension systems, sheaves, and governors.
• Car and counterweight guide systems.
• Traveling cables, hoistway wiring, and fixtures.
• Existing safety equipment and code-related deficiencies.
• Equipment obsolescence and replacement parts availability.
Some components may remain suitable for continued service, while others require replacement due to deterioration, poor reliability, limited manufacturer support, or incompatibility with new equipment.
What owners should do: Obtain an independent equipment condition assessment before establishing the modernization scope.
The assessment should identify which components require replacement, which may be retained, and which warrant additional testing or engineering review.
Replacing serviceable equipment unnecessarily increases capital costs. Retaining deteriorated or incompatible equipment can create expensive problems after modernization.
2. Accepting a Contractor's Proposal Without Independent Specifications
Another costly mistake is requesting modernization proposals from multiple elevator contractors without first establishing a common technical specification.
Each contractor may propose different equipment, components, performance criteria, exclusions, and project responsibilities.
For example, one proposal may include replacement of hoistway door equipment, traveling cables, fixtures, and electrical wiring, while another may retain some of these components.
Although the second proposal may appear less expensive, the difference may simply reflect a reduced scope of work.
A lower modernization price does not necessarily represent a lower project cost or better long-term value.
A properly prepared modernization specification should establish:
• Equipment and component replacement requirements.
• Acceptable equipment performance and quality standards.
• Controller and drive requirements.
• Door operating equipment and performance criteria.
• Retained equipment and required interface work.
• Safety and code compliance requirements.
• Electrical, mechanical, and building interface responsibilities.
• Project schedule and elevator shutdown limitations.
• Testing, inspection, and acceptance requirements.
• Warranty, maintenance, training, and documentation obligations.
What owners should do: Develop an independent, detailed modernization specification before soliciting competitive bids.
This allows qualified contractors to price substantially the same scope of work and helps reduce misunderstandings, omissions, and change orders.
3. Overlooking Proprietary Equipment and Long-Term Maintenance Restrictions
Equipment selection can have a significant effect on future maintenance costs and contractor flexibility.
Some elevator control systems require manufacturer-specific software, diagnostic tools, replacement components, or technical support.
These restrictions may limit the ability of independent maintenance contractors to troubleshoot and repair equipment.
Potential long-term consequences include:
• Limited competition for maintenance services.
• Higher replacement component costs.
• Restricted access to diagnostic software.
• Longer repair times when specialized support is required.
• Dependence on a particular manufacturer or authorized service organization.
However, equipment described as nonproprietary is not necessarily fully open or independently maintainable.
What owners should do: Require bidders to disclose all restrictions associated with equipment diagnostics, software access, replacement parts, technical documentation, and future maintenance.
Specifications should clearly define the required access rights, diagnostic capabilities, tools, documentation, and support arrangements available to the owner and future qualified maintenance providers.
These requirements should be verified during submittal review and before final project acceptance.
4. Failing to Evaluate Existing Building Conditions
Elevator modernization frequently involves more than replacing equipment within the hoistway or machine room.
Older buildings may contain electrical, structural, mechanical, and life-safety conditions that require modification to accommodate new elevator equipment.
Potential issues include:
• Inadequate electrical service capacity.
• Existing feeders and disconnects that require replacement.
• Insufficient machine-room ventilation or cooling.
• Limited machine-room or hoistway clearances.
• Inadequate structural support for replacement equipment.
• Hoistway and pit water intrusion.
• Fire alarm and emergency power interface deficiencies.
• Inadequate access for equipment removal and installation.
• Existing conditions that do not satisfy applicable modernization requirements.
For example, replacing an older elevator controller with modern power electronics may introduce different electrical and environmental requirements.
Similarly, a new traction machine may require structural evaluation, mounting modifications, or revised electrical distribution.
What owners should do: Perform a preconstruction building conditions survey involving the appropriate elevator, electrical, mechanical, structural, and fire protection professionals.
Identify and assign responsibility for building-related work before issuing the final bid documents.
5. Underestimating Elevator Shutdowns and Building Operations
Elevator modernization requires equipment to be removed from service, often for an extended period.
Poor shutdown planning can significantly affect building operations, particularly in hospitals, residential towers, hotels, senior living facilities, and high-occupancy commercial properties.
Operational considerations include:
• Number of elevators remaining in service.
• Passenger traffic and peak operating periods.
• Accessibility and mobility needs.
• Emergency response and evacuation procedures.
• Freight, deliveries, and service requirements.
• Construction noise and restricted work areas.
• Tenant communication and project sequencing.
Modernizing several elevators simultaneously may reduce certain construction costs but create unacceptable operational disruption.
What owners should do: Establish a phased modernization schedule based on the building's operating requirements.
Where appropriate, conduct an elevator traffic analysis to determine whether the remaining elevators can accommodate building demand during construction.
Contract documents should define shutdown durations, sequencing, work-hour restrictions, milestones, and contractor responsibilities.
6. Selecting Equipment Without Establishing Performance Requirements
Modernization should not simply restore an elevator to its previous operating condition.
It should address documented performance deficiencies and establish appropriate requirements for future service.
Performance criteria may include:
Performance factor Technical consideration
Contract speed Rated operating speed and acceptable performance
Floor leveling Stopping accuracy and accessibility requirements
Door operation Opening and closing performance, protection, and reliability
Ride quality Acceleration, deceleration, vibration, and passenger comfort
Dispatching Group supervisory operation and traffic handling
Equipment capacity Suitability for current building demand
Energy performance Drive efficiency, regeneration where appropriate, and standby consumption
Reliability Equipment availability, fault monitoring, and maintenance requirements
The required performance criteria should reflect the equipment type, building usage, applicable codes, and project objectives.
What owners should do: Include measurable performance requirements in the modernization specifications and verify them through appropriate acceptance testing.
7. Failing to Address Code Compliance Early
Modernization projects can trigger specific safety, accessibility, electrical, fire protection, and building code requirements.
The applicable requirements depend on the jurisdiction, adopted code editions, equipment type, and extent of alteration.
Potential considerations include:
• Elevator safety requirements under the applicable ASME A17.1/CSA B44 edition.
• Applicable existing-elevator requirements and alteration provisions.
• Firefighters' emergency operation.
• Door protection and monitoring requirements.
• Emergency communication systems.
• Accessibility requirements.
• Electrical equipment and wiring.
• Emergency or standby power interfaces.
• Inspection, testing, permitting, and acceptance requirements.
What owners should do: Identify applicable code requirements during the planning and specification phase.
Coordinate with the authority having jurisdiction and appropriate design professionals before finalizing the project scope.
Late discovery of required upgrades can produce substantial change orders and delay final acceptance.
8. Overlooking Change Orders and Hidden Project Costs
A modernization proposal may exclude work that is necessary to complete the project.
Common exclusions or cost risks include:
• Electrical service and feeder modifications.
• Machine-room cooling and ventilation.
• Structural engineering and equipment support.
• Fire alarm and emergency power modifications.
• Hoistway repairs and associated building work.
• Hazardous material identification and abatement.
• Permits, inspections, and testing responsibilities.
• Equipment storage, rigging, and access requirements.
• Temporary protection and restoration of building finishes.
• Additional work resulting from concealed conditions.
Owners should distinguish between legitimate unforeseen conditions and changes caused by incomplete specifications or inadequate contractor coordination.
What owners should do: Require bidders to identify exclusions, allowances, assumptions, unit prices, and potential additional costs.
Establish a documented change-order procedure requiring technical justification, cost breakdown, schedule impact, and written authorization before additional work proceeds, except where immediate safety action is required.
A project contingency should be established based on the age of the building, available records, site conditions, and uncertainty in the scope.
9. Inadequate Construction Oversight and Quality Control
Even well-written specifications cannot guarantee a successful modernization without proper construction oversight.
Potential problems include:
• Installation of components that differ from approved submittals.
• Improper mechanical alignment or adjustment.
• Inadequate wiring identification and documentation.
• Poor workmanship or incomplete equipment installation.
• Failure to coordinate building interfaces.
• Incomplete testing and commissioning.
• Unresolved punch-list deficiencies.
What owners should do: Establish a construction administration and inspection process that includes:
1. Review of contractor equipment submittals.
2. Verification of major equipment and material selections.
3. Periodic installation observations.
4. Documentation of deficiencies and corrective actions.
5. Coordination of testing and inspection requirements.
6. Review of final performance and acceptance results.
Independent technical oversight can help identify deficiencies before they become costly or difficult to correct.
10. Accepting the Elevator Before the Project Is Truly Complete
Final acceptance should involve more than confirming that the elevator travels between floors.
Before accepting the project, owners should verify that the specified equipment has been installed, required tests have been completed, and project documentation has been delivered.
Important closeout items include:
• Required inspection and acceptance test records.
• Resolution of outstanding deficiencies.
• Verified operating and performance requirements.
• As-built electrical drawings and wiring diagrams.
• Controller and equipment documentation.
• Diagnostic tools, access credentials, and software rights required by the contract.
• Maintenance and operating instructions.
• Equipment warranties and spare parts information.
• Training for designated building personnel, where appropriate.
• Required permits and jurisdictional approvals.
What owners should do: Establish a written project closeout checklist and verify contractual completion before authorizing final payment, subject to the contract's payment provisions.
Any unresolved deficiencies should be documented with assigned corrective responsibilities and completion dates.
11. Failing to Plan for Maintenance After Modernization
Modernization does not eliminate the need for preventive maintenance.
New elevator equipment requires properly trained technicians, manufacturer-recommended procedures, appropriate diagnostic resources, and a maintenance program suited to the installed systems.
Building owners should evaluate:
• Warranty coverage and exclusions.
• Initial maintenance obligations.
• Technician training and qualifications.
• Preventive maintenance requirements.
• Parts availability and technical support.
• Future maintenance contractor access.
• Service response and equipment reliability expectations.
What owners should do: Establish the post-modernization maintenance strategy before awarding the modernization contract.
This helps ensure that the selected equipment can be properly maintained throughout its expected service life.
A Practical Modernization Checklist for Building Owners
Before authorizing a modernization project, confirm the following:
• An independent equipment condition assessment has been completed.
• Equipment replacement and retention decisions are documented.
• Detailed technical specifications have been prepared.
• All bidders are pricing a comparable scope of work.
• Proprietary equipment and diagnostic restrictions have been evaluated.
• Existing building conditions have been investigated.
• Applicable code and accessibility requirements have been identified.
• Elevator shutdowns and construction sequencing have been planned.
• Performance requirements and acceptance criteria are established.
• Contractor exclusions and potential change orders have been reviewed.
• Construction oversight and testing responsibilities are defined.
• Warranty, maintenance, documentation, and closeout requirements are included.
Conclusion
Elevator modernization is a long-term investment that requires careful technical evaluation, detailed planning, competitive procurement, and effective project management.
Many of the most expensive modernization mistakes occur before construction begins—when equipment is selected without a comprehensive assessment, bids are solicited without detailed specifications, building conditions are overlooked, or future maintenance restrictions are not considered.
The lowest initial modernization proposal is not always the most economical solution.
A successful project should balance initial construction cost, equipment reliability, long-term maintainability, passenger performance, safety, and the building owner's operational needs.
By establishing clear technical requirements, evaluating competing proposals on a consistent basis, and maintaining independent oversight throughout the project, building owners can reduce financial risk and improve the long-term value of their elevator modernization investment.
HOW SENAWI GROUP CONSULTING LLC CAN HELP
Senawi Group Consulting LLC provides independent elevator, escalator, and moving walk consulting services for building owners, property managers, architects, engineers, and facility professionals.
Our modernization consulting services include:
• Comprehensive equipment condition assessments.
• Modernization feasibility studies and capital planning.
• Modernization design and technical specifications.
• Competitive bidding and contractor proposal evaluations.
• Equipment selection and maintainability evaluations.
• Construction administration and project oversight.
• Equipment testing, performance evaluations, and project closeout reviews.
With more than 39 years of elevator industry experience, Senawi Group Consulting provides independent technical guidance to help building owners make informed decisions and protect their capital investments.
Karl Senawi, Ph.D.
President | Senawi Group Consulting LLC
Phone: 248-763-7300
Email: senawik@senawiconsulting.com
Website: www.senawigroupconsulting.com
ELEVATING PERFORMANCE. DELIVERING SOLUTIONS.
Technical note: Modernization requirements vary by jurisdiction, equipment type, existing conditions, and adopted code editions. Project-specific engineering, code review, and qualified professional evaluations are necessary before implementing modernization work.